01
Scheduling system was developed within Oracle Primavera software.
|
02
Construction and mantling works were optimized by LMP Project Group team with direct participation of the operators based on the data regarding their performance and supply deadlines.
|
03
Monthly correction was performed in terms of the resource volumes needed for mantling process, considering the material difference of the weight of the metal structures actually supplied from the ones initially stated in the design documentation.
|
04
Calculation was performed in terms of required labor and technical resources of the general contractor and customer.
|
05
Supplies of equipment and metal structures to the construction facilities, as well as construction and mantling works were coordinated.
|
accurate construction and mantling schedule was prepared for the whole construction period;
|
metal structures and equipment mantling process was optimized taking the supplies deadlines into account, which resulted in minimization of idle time;
|
adequate quantity of the necessary resources was determined.
|